SAP PP — Check the production master data
- Material and components
- Use a manufactured material with a suitable bill of material. A bill of material lists the components needed for the product.
- Operations and resources
- A routing describes the work steps and work centres. Check the relevant production version where your process uses one.
- Stock and dates
- Confirm available component stock, the plant and the planned production dates before releasing the exercise order.
Example: make 3 practice units
Inspect the order
Review the quantity, components, operations and planned dates.
Release and prepare
Follow the permitted release procedure and resolve relevant availability messages.
Record production
Post or inspect the required component consumption and operation confirmation. Automatic movements depend on the configuration.
Receive the output
Review the finished-goods receipt, stock change and order status. Compare the actual result with the order quantity.
If something differs
Components are missing
Check the plant, stock location, required quantity and material availability before changing the order.
Confirmation and stock disagree
Review automatic versus manual movement settings and any failed goods movements associated with the confirmation.
ERP SERVER ACCESS
How our access fits

Our S/4HANA 2023 environment can support compatible PP practice and its MM/CO connections. Confirm specialist planning tools or production scenarios separately from basic order processing. Individual access includes SAP_ALL for all functional T-codes, SPRO configuration and ABAP development on S/4HANA 2023.
SAP references
Consult SAP’s documentation for your product and release. The examples in this guide are for practice.